This report provides information such as variations, available fees, total invoiced, debtors and billable values. It can be sorted by project code.
Show Phase Active Status is included in the report if sub-projects are enabled. It shows a Y or an N beside the phase name.
The billable amount will only be shown if the relevant phase is marked as 100% complete. The allocated amount of the phase is deemed to be the billable value of that phase.
Revised Project Surplus / Deficit column =Allocated Fee - Projected Final Charge
where
Projected Final Charge = Time and Expense x Fraction Complete
(For example, if project time and expense is half complete, Fraction Complete = 0.5)